Construction Projects

Project Updates

Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $1,491,759.27
  • Start Date:
    • 9th Street SW – May 2, 2024
    • 12th Street SW – Mid-July
  • Project Updates:
    • June 10, 2024 – The contractor will be finishing up sanitary sewer main, and Austin Utilities will be finishing up water main work on 9th St SW this week.
    • June 3, 2024 – This week, the contractor will continue working on sanitary sewer south of 19th Ave, while Austin Utilities continues working on water services north of 19th Ave.
    • May 28, 2024 – The contractor will be working on sanitary sewer on 19th Ave this week. Austin Utilities will continue water main and service replacement on 9th St.
    • May 21, 2024 – On Thursday morning, the contractor will begin pavement removal in the 19th Ave intersection. Please make sure your vehicles are parked outside of the traffic barricades. Following pavement removal, they will be working on sanitary manhole replacement north of 19th Ave. Austin Utilities will also continue water main work north of 19th Ave. After Memorial Day weekend, the contractor will begin working on sanitary sewer south of 19th Ave.
    • May 14, 2024 – Austin Utilities will continue water main and service replacement on 9th St SW this week. Sanitary sewer work is expected to begin next week.
    • April 30, 2024 – The contractor has completed work on another street in Austin earlier than expected. They plan to move equipment to 9th St SW this afternoon and begin pavement removal. They will limit their work to one half of the street to maintain traffic. Driveways will remain accessible until Thursday. On Thursday they will begin removing the remaining pavement.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 9th St SW is planned to begin on Thursday, May 2nd.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $1,224,850.00
  • Start Date:
    • 2nd Ave NW (14th St to 18th St NW) – May 7, 2024
    • 2nd Ave NW (18th St to 19th St NW) – Late June
    • 16th St NW & 17th St NW – Mid-August
  • Project Updates:
    • June 10, 2024 – Austin Utilities will continue working on water main replacement on 2nd Ave between 14th St & 16th St this week.
    • June 3, 2024 – This week the contractor will begin removing the concrete pavement on 2nd Ave NW from 16th St to 14th St. Austin Utilities will continue with water main and service replacements.
    • May 28, 2024 – Austin Utilities will continue water service replacement on 2nd Ave NW this week.
    • May 21, 2024 – This week Austin Utilities will continue water main replacement and begin water service replacement on 2nd Ave NW.
    • May 14, 2024 – Austin Utilities will be setting up temporary water service and begin water main replacement this week
    • May 1, 2024 – Work on 2nd Ave NW between 16th St and 18th St NW is planned to begin on Monday, May 7th. Please park all vehicles on adjacent open streets.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 2nd Ave NW from 16th St to 18th St NW is planned to begin on Tuesday, May 7th. They will then begin work on 2nd Ave NW between 16th St and 14th St NW later in May. Work on 2nd Ave NW from 18th St to 19th St NW will begin in June. Work on 16th St & 17th St NW will begin in August.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $453,409.60
  • Start Date: April 29, 2024
  • Project Updates:
    • June 10, 2024 – The contractor will continue roadway excavation and begin sidewalk replacement this week.
    • June 3, 2024 – The contractor expects to begin drain tile and roadway excavation this week.
    • May 28, 2024 – The contractor will begin drain tile and roadway excavation this week.
    • May 21, 2024 – The contractor will be completing storm sewer replacement this week.
    • May 14, 2024 – Austin Utilities has completed water main replacement. Storm sewer work is expected to begin at the end of the week.
    • May 1, 2024 – Work has begun on 1st Ave NE. The contractor has completed removals. Austin Utilities will now be working on water main replacement.
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 1st Avenue NE is planned to begin on Monday, April 29th.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Icon, LLC
  • Project Cost: $829,156.20
  • Start Date:
    • 17th St NE to 1900 4th Ave NE – Late June or Early July
    • 1900 4th Ave to 19th St NE – Late July
  • Project Updates:
    • April 17, 2024 – A pre-construction meeting was held with the contractor, ICON. Work on 4th Ave NE is planned to begin in mid-June.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 1, 2024 – Bids for the project were opened on March 25th. The low bidder was ICON, LLC. The Austin City Council awarded the construction contract to ICON, LLC at the April 1st council meeting.
Project Info
Project Phasing & Schedule
Feasibility Report
Project Map

  • Contractor: Ulland Bros, Inc.
  • Project Cost: $2,464,584.00
  • Start Date: June 24, 2024
  • Project Updates:
    • June 11, 2024 – The contractor plans to begin work on the project the week of June 24th.
    • May 21, 2024 – Work on the project is now expected to begin on June 5th.
    • April 30, 2024 – A pre-construction meeting was held with the contractor, Ulland Bros. Work is planned to begin on the project on May 28th.
    • April 15, 2024 – Bids for the project were opened on April 9th. The low bidder was Ulland Bros, Inc. The Austin City Council awarded the construction contract to Ulland Bros, Inc. at the April 15th council meeting.
    • February 14, 2024 – Public Open House held at City Hall to present information about street reconstruction projects.
    • February 20, 2024 – Public Hearing on project improvements held at the City Council meeting.
    • March 18, 2024 – Public Hearing on Assessments was held at the City Council meeting.
    • April 15, 2024 – Bids for the project were opened on April 9th. The low bidder was Ulland Bros, Inc. The Austin City Council awarded the construction contract to Ulland Bros, Inc. at the April 15th council meeting.

5 Year Capital Improvement Plan